National Highways – A1 Brampton Hut Roundabout Roadworks Monday 28th September for 8 weeks
National Highways Important roadworks information
A1 Brampton Hut Roundabout – Drainage kerb upgrade and resurfacing
We’re planning to carry out essential repairs and maintenance at the A1 Brampton Hut roundabout. We’ll improve and strengthen the drainage kerbs, resurface the road and replace the road markings and traffic signal sensors. Once complete, these improvements will help surface water drain away more effectively and reduce the risk of flooding.
We plan to complete this work in phases over eight weeks starting on Monday 28 September. We will work overnight between 9:30pm and 5am on weeknights and one full weekend, weather permitting.
Closures and diversions
To carry out the work safely, we will need to close parts of the A1 Brampton Hut Roundabout and A141 eastbound link, and divert traffic as follows:
|
Closure? |
Date? |
Diversion? |
|
Phase 1 A1 Northbound exit slip and entry road into services. The exit from the services will remain open. |
Monday 28 September to Wednesday 14 October 2026
Monday – Friday 9.30pm – 5am |
|
|
Phase 2 A141 eastbound link between A14 junction 21 and Brampton Hut Roundabout. Please note, dates for phases 1 & 2 will run in parallel. |
Monday 28 September to Friday 16 October 2026
Monday – Friday 9.30pm – 5am |
|
|
Phase 3 Inner lane of Brampton Hut Roundabout (north and west quadrant) |
Monday 12 October to Thursday 19 November 2026
Monday – Friday 9.30pm – 5am |
|
We will be carrying out a fourth phase, which will require a full weekend closure of the Brampton Hut Roundabout from 9.30pm Friday 20 November until 5am Monday 23 November. We’ll write to you again with more details.
For the duration of the works a lane closure will remain in place on the roundabout during the day for safety reasons and to protect the work area.
Please note emergency vehicles will have access through the works with caution.
Maps of the diversions can be found below.
How to find out more
To find out more about road improvements we’re carrying out across the East of England, please visit our website at https://nationalhighways.co.uk/our-work/
If you would like more information, please contact us on 0300 123 5000, or by email at info@nationalhighways.co.uk.
Yours faithfully
Gemma Timson
Project Manager
Operations East, Scheme Delivery Team